ppc.land Belgian region halts Google data centre over unpermitted 3-hectare building Luis Rijo 24–30 minutes

Inspectors sent by the Walloon Region ordered Google to stop construction on a data centre at the Ecopôle business park in Aiseau-Presles, in the Belgian province of Hainaut, on Thursday, November 26, 2026, after finding a building of 30,000 square metres almost finished even though the permit change it depended on had been refused in August. About 300 workers on site received a verbal order to down tools. A day later, on November 27, a regional government spokesperson said a report alleging "a major offence" was being sent to public prosecutors, according to The Guardian, which cited Agence France-Presse. In Short

Belgian regional inspectors stopped work on a large Google data centre near Charleroi on November 26, 2026, because the building matched a version of the project that the Walloon government had refused in August. The refused version would have merged two planned buildings into one larger one and cooled it with water from the Sambre river, which the minister rejected over water needs during a drought. Google is challenging that refusal before Belgium's highest administrative court, with a public hearing set for January 7, 2027, and the region is now sending a report on the construction to prosecutors. The environmental group Greenpeace, which pushed for the halt, calls the site illegal, while the minister's office said the original 2024 permit for three smaller buildings remains valid. What the inspectors found

Raphaël Stokis is the region's "fonctionnaire délégué", the civil servant who handles planning permits and their enforcement in the area. Speaking to the Belgian public broadcaster RTBF, he described the visit in detail. The following is a translation from French.

"Inspectors went to the site on Thursday," Stokis said, according to RTBF. "We found that a building of 30,000 square metres, 3 hectares, was almost finished, with the structural shell closed, even though the permit had been refused by the minister. There were some 300 workers on site, to whom we gave a verbal order to stop the work. This verbal order will be confirmed in writing to Google."

"Structural shell closed" is the French building term "gros oeuvre fermé": walls and roof up, interior fit-out not done. In other words, the building was not a foundation slab or a set of steel columns. It was a closed hall the size of roughly four football pitches, using the ratio RTBF applies to the whole site (PPC Land calculation).

The Guardian, in a report by Jon Henley published on November 27 at 18:21 CET, gave Stokis's quote in English: "Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused." The same report said the verbal order "had been confirmed in writing to Google." RTBF's November 26 report, filed at 17:33, said the written confirmation was still to come. The articles do not show which version reflects the situation on November 27.

Nicolas Yernaux, a regional government spokesperson, went further on Friday, November 27. He told Agence France-Presse that a report was being submitted to public prosecutors alleging "a major offence: the illegal construction of a building covering 3 hectares", according to The Guardian.

Google's response was short. According to RTBF, which called it "very laconic", the company said: "we are committed to maintaining an open and collaborative dialogue with the regional government and experts regarding our investments in Wallonia." That sentence is translated from French. The Guardian quoted the English wording as "committed to maintaining an open and collaborative dialogue" with the regional authorities. Neither report carries a Google comment on the permit question itself. RTBF said on November 25 that it had contacted Google Belgium's spokesperson and received no answer at the time of publication. Two permits, one site

The dispute turns on the difference between two versions of the same project. Google is building at the Ecopôle through its European subsidiary Crystal Computing, according to RTBF. The broadcaster describes the overall development as a complex of data centres spread over 53 hectares, "the equivalent of 74 football pitches", straddling three municipalities: Farciennes, Aiseau-Presles and Sambreville. The Guardian describes a 50-hectare business park on the site of a former coal mine, about 15 kilometres from Charleroi. Item 2024 permit 2025 modification Number of data centres Three smaller buildings Two, after merging two of the three into one larger building Cooling Air cooling Water drawn from the Sambre river Planned water draw None stated 600 cubic metres an hour (The Guardian) Same draw per day Not applicable 14,400 cubic metres (PPC Land calculation) Approval Granted in 2024 Approved by the Walloon administration in April 2026 Current status Still valid, according to the minister's office Refused by minister François Desquesnes in August 2026

The 600-cubic-metre figure comes only from The Guardian. The daily figure above is a straight multiplication by 24 hours; none of the reports says whether the draw would run around the clock or only at peak load.

The original permit, granted in 2024, covered three "small" data centres cooled by air, according to RTBF and Greenpeace. In 2025, Google changed its request: it wanted to merge two of the three buildings into a single, much larger one and switch from air cooling to water taken from the Sambre. The Walloon administration approved that modification in April 2026. A month later, residents lodged an appeal against it, according to RTBF.

In August 2026, François Desquesnes, the Walloon minister for spatial planning, infrastructure and local authorities and a member of the centrist party Les Engagés, refused the modification. According to RTBF, he "pointed to the data centre's water needs to justify his decision." The decision came, as Greenpeace noted and RTBF relayed, while Belgium was going through a historic drought. The Guardian put it more briefly: the minister "revoked the modified permit over drought concerns." What the minister's office said before the halt

The legal position was less clear-cut than the word "illegal" suggests, and RTBF set this out on November 25, the day before the inspection. The minister's office told the broadcaster that the initial permit delivered in 2024 "reste valable" - "remains valid". RTBF spelled out what that meant in practice: if Google follows the plans in the original permit, three "small" data centres, it is within the rules. If it builds the two "large" data centres of the 2025 modification, it is in breach.

The office then described the next step. "Regional officers will carry out checks to make sure that the work under way complies with the valid permit," the minister's office said, according to RTBF. It added: "If defects are found, an official report will be drawn up. The on-site checks will not drag on. If there is a report, it will be sent to the public prosecutor's office." Both statements are translated from French. The French term for the report is "PV", short for "procès-verbal", the formal record of an offence that Belgian officials pass to prosecutors.

Within roughly 24 hours, that is what happened. Stokis's finding on November 26 was that the 3-hectare building did not match the permit that remains valid. Yernaux's statement on November 27 confirmed the report was on its way to prosecutors. How the stop order came about

The four reports describe a sequence of steps that runs from a citizens' appeal in spring 2026 to a prosecutors' file in late November. According to the sources, it unfolded in eight stages.

Modification approved. The Walloon administration approved Google's 2025 permit modification in April 2026, according to Greenpeace and RTBF.
Citizens' appeal. Residents appealed against the modification about a month later, according to RTBF.
Ministerial refusal. In August 2026, minister Desquesnes refused the modification on appeal, citing the data centre's water needs, according to RTBF and The Guardian.
Court challenge. On October 17, 2026, Google filed a request with the Conseil d'Etat, Belgium's highest administrative court, to annul the minister's decision and to suspend it in the meantime, according to Greenpeace.
Interveners join. On November 16, several residents and Greenpeace filed a request to intervene in that case so they could argue their side, according to Greenpeace.
Emergency request. Alerted by residents that work was continuing, Greenpeace investigated and, early in the week of November 23, wrote to the Walloon government asking for the work to be suspended immediately. RTBF dated this emergency action to Wednesday, November 25, and said it went to the minister's office.
Inspection and verbal order. On Thursday, November 26, inspectors sent by the regional delegated official visited the site and verbally ordered about 300 workers to stop, according to Stokis via RTBF. The order was to be confirmed in writing to Google.
Report to prosecutors. On Friday, November 27, a regional spokesperson said a report alleging the illegal construction of a 3-hectare building was being sent to prosecutors, according to The Guardian.

The Conseil d'Etat has scheduled a public hearing for January 7, 2027, according to Greenpeace and RTBF. Greenpeace's case

Greenpeace Belgium is an environmental campaign group and a party to the court case, so its statements are advocacy, not neutral findings. Its press release, dated November 27, 2026, is titled "La Région wallonne suspend la construction du data center de Google à la suite d'une enquête de Greenpeace" ("The Walloon Region suspends construction of Google's data center following a Greenpeace investigation"). The release itself relies on media reports for the halt: the region ordered the work stopped, "as could be read in several media outlets last night," it says.

"Tech giants are not above the law," said Nadia Cornejo, a spokesperson for Greenpeace Belgium, according to the release. "We are pleased to learn that the site is now at a standstill. That should already have been the case in August, when the permit was annulled. This is a first victory for citizens and the environment. But we continue to watch closely what is happening in Aiseau-Presles. The construction in our country of hyperscale data centres, as hungry for water as they are for energy, concerns all of us and cannot go under the radar." The quote is translated from French.

On November 25, Cornejo had been sharper. "That Google continues to build while its permit is annulled gives an idea of the respect the multinational has for our regulations, our resources, the impact on our territories and on our citizens," she said, according to RTBF, in a translated quote. She added that the arrival of data centres "is a real debate for society and cannot remain confined to discreet agreements between industrial companies and our administrations."

The Guardian quoted Greenpeace in English: "The tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked." It also carried the group's warning: "The climate crisis will only intensify in our region. Against this backdrop, the construction of energy-guzzling behemoths cannot be allowed to go unnoticed."

How did Greenpeace know the work was continuing? RTBF said the group relied on satellite images. The Guardian said Greenpeace published a report "including drone footage". The two descriptions may refer to different parts of the same material; the reports do not say.

Greenpeace also pointed to Google's existing Belgian site. According to the group, as reported by RTBF, a similar Google project already built at Saint-Ghislain, near Mons, draws 1 billion litres of water a year to cool its data centres, and only a quarter of that water is returned, the rest evaporating in the cooling process. Those figures are Greenpeace's. Google's response to them is not in the reports. Where the reports disagree

The four reports agree on the core facts: a halt on November 26, a 3-hectare building, about 300 workers, a refused permit change and a January 7 hearing. They differ on several details. Point Version one Version two Year of the change request 2025 (Greenpeace, RTBF on Nov 25, The Guardian) 2024 (RTBF on Nov 26) What happens on January 7 Public hearing (Greenpeace, RTBF) Ruling expected (The Guardian) Written stop order To be confirmed in writing (RTBF) Already confirmed in writing (The Guardian) Greenpeace's evidence Satellite images (RTBF) Drone footage (The Guardian) Permit status Permit "annulled" (Greenpeace) or "suspended" (RTBF summary, Nov 25) Only the change was refused; 2024 permit valid (minister's office) Workers About 300 on site on Nov 26 (Stokis) 1,200 working for months (RTBF, Nov 25)

The worker figures are not necessarily in conflict: 1,200 describes the project's workforce over months, while 300 is the headcount inspectors found on one day. The permit wording matters more. Greenpeace speaks of a permit being annulled, which suggests the site has no valid authorisation at all. The minister's office says the opposite about the 2024 permit. The case against Google, as described by Stokis and Yernaux, is narrower: one building that matches the refused plan.

There is also a numbering question. RTBF's November 26 headline calls the halted building Google's "second data center" on the site. The Guardian says it is "one of three originally planned". Both can be true at once, since the 2025 plan would have turned three planned buildings into two. Europe's second Google halt in two months

Belgium is not the only European country where Google's building programme has run into the permit system this autumn. PPC Land reported on October 6, 2026 that Finland's Permit and Supervision Agency sent a Google subsidiary two notices calling for land-altering preparatory work at Muhos and Kajaani to be suspended by October 23, 2026. About 330 hectares had been cleared at Muhos and just under 200 at Kajaani-Otanmäki. Cooling water at those sites is planned to come from the Oulujoki river and Lake Oulujärvi.

The Guardian's November 27 report adds that Finland opened a criminal investigation in October into possible breaches of environmental law at a planned Google data centre in the country's rural north, and that work has been halted until environmental impact assessments are completed.

The pattern is not uniform. In Austria, Google broke ground at Kronstorf on April 23, 2026 after the local building-law procedure was completed and approved in January 2026, almost 18 years after it bought the land. In Sweden, the company started construction at Horndal on June 2, 2026 with an air-cooled design and court permission obtained in 2021. Water, and how a building is cooled, keeps coming up in these decisions.

Opposition is not new in the United States either. In September 2025, Google withdrew its rezoning request for a $1 billion project in Indianapolis minutes before a council vote, after residents gathered more than 2,400 signatures. In August 2026, PPC Land covered research by Data Center Watch showing that local opposition blocked or delayed at least $156 billion of data centre projects in 2025, with polling by Heatmap putting US opposition to a nearby data centre at 75% in August 2026, up from 42% a year earlier.

Data centres look remote from campaign dashboards. They are not. Google's data centres are where the company trains and runs the models behind AI Overviews, AI Mode, Gemini and the automated bidding and creative tools sold to advertisers, and they are paid for largely by advertising. In the fourth quarter of 2025, Alphabet's advertising revenue reached $81.5 billion out of $113.8 billion in total revenue, and the company guided 2026 capital spending to $175 billion to $185 billion at the time.

That figure has since grown. In the third quarter of 2026, Alphabet spent $51.4 billion on capital expenditure, up 114%, and its free cash flow turned negative for the quarter: minus $9.1 billion despite a $26.2 billion profit. The full-year guidance set in July stood at $195 billion to $205 billion. The reports on Aiseau-Presles give no figure for what the halted building cost, or what a delay would cost.

Google is one of the three cloud companies at the core of the hyperscaler group, firms that build computing capacity at a scale few others can match. Google and Amazon both publish water figures for their operations. Google said its stewardship projects replenished about 7.7 billion gallons of water in 2025, roughly 78% of its freshwater consumption that year. Amazon reported in June 2026 that its data centres used 0.12 litres of water per kilowatt-hour in 2025, against an industry average of 0.84. In Oregon, Google handed an aquifer storage system to the city of The Dalles in October 2025, adding more than 100 million gallons a year of capacity. In Georgia, by contrast, a New York Times investigation covered by PPC Land linked Meta's Newton County data centre to about 10% of the county's daily water use.

The Walloon case shows how such pledges meet a specific river in a specific dry summer. The minister did not reject data centres at the Ecopôle; the 2024 permit for three air-cooled buildings still stands, according to his office. What he refused was a larger building cooled with water from the Sambre. For companies that buy AI-driven advertising and for publishers whose traffic increasingly runs through AI answers, the practical question is capacity: where it gets built, how quickly, and under what conditions. Wallonia has now shown that a regional planning official can stop a nearly finished hall in a single site visit. What the reports do not say

None of the four reports gives the value of the investment at Aiseau-Presles, the electrical capacity of the halted building, the date construction of that building began, or Google's legal argument before the Conseil d'Etat. They do not say whether the 600-cubic-metre hourly water draw is a peak or a continuous figure, which prosecutor's office will receive the report, or whether the stop order covers the whole Ecopôle site or only the 3-hectare building. Google's view on whether the building complies with the 2024 permit is not given. Key facts Item Detail Site Ecopôle business park, Aiseau-Presles, with parts in Farciennes and Sambreville, Hainaut, Belgium Developer Google, through European subsidiary Crystal Computing (RTBF) Halted building About 30,000 square metres (3 hectares), structural shell closed Workers on site at the halt About 300 Date of halt Thursday, November 26, 2026 (verbal order) Ordering authority Inspectors sent by the delegated official of the Walloon Region, Raphaël Stokis Report to prosecutors Announced November 27, 2026 by regional spokesperson Nicolas Yernaux Refused modification Merge two of three buildings into one; switch from air to water cooling from the Sambre Refusal August 2026, minister François Desquesnes (Les Engagés) Google's appeal Filed October 17, 2026 with the Conseil d'Etat (annulment and suspension) Intervention Filed November 16, 2026 by residents and Greenpeace Court date Public hearing, January 7, 2027

Sources: Greenpeace Belgium, "La Région wallonne suspend la construction du data center de Google à la suite d'une enquête de Greenpeace", press release, November 27, 2026 (greenpeace.org/belgium/fr). The Guardian, "Google told to halt Belgium datacentre construction over lack of planning permit", Jon Henley, November 27, 2026, 18:21 CET. RTBF, "Aiseau-Presles : Google poursuit les travaux d'un data center sans permis adéquat, dénonce Greenpeace", Belga newsroom, Simon Gérard and Vincent Clérin, November 25, 2026, 09:46, updated November 26, 2026, 16:09. RTBF, "Google contraint d'interrompre les travaux de son second data center sur le chantier de Farciennes/Aiseau-Presles", Nicolas Rondelez and Maïté Warland, November 26, 2026, 17:33. Timeline

2024 - The Walloon Region grants Google a permit for three smaller, air-cooled data centres at the Ecopôle.
2025 - Google applies to modify the permit: two buildings instead of three, and water cooling from the Sambre (RTBF on November 26 dates the request to 2024).
July 21, 2025 - PPC Land reports that Meta's Newton County, Georgia data centre uses about 10% of the county's daily water.
September 22, 2025 - Google withdraws its rezoning request for a $1 billion data centre in Indianapolis.
October 22, 2025 - Google completes the transfer of an aquifer storage system to The Dalles, Oregon.
February 4, 2026 - Alphabet reports $81.5 billion of fourth-quarter 2025 advertising revenue and guides 2026 capital spending to $175 billion to $185 billion.
April 2026 - The Walloon administration approves the permit modification.
April 23, 2026 - Google breaks ground at Kronstorf, Austria.
May 2026 - Residents appeal against the modification, about a month after approval.
June 2, 2026 - Google breaks ground on an air-cooled data centre at Horndal, Sweden.
June 11, 2026 - Amazon reports water use of 0.12 litres per kilowatt-hour for 2025.
June 30, 2026 - Google's environmental report says it replenished about 7.7 billion gallons of water in 2025.
August 2026 - Minister François Desquesnes refuses the modification, citing water needs during a drought.
August 30, 2026 - PPC Land reports that local opposition blocked or delayed $156 billion of data centre projects in 2025.
October 6, 2026 - Finland's Permit and Supervision Agency sends a Google subsidiary two notices to suspend work at Muhos and Kajaani.
October 17, 2026 - Google asks the Conseil d'Etat to annul and suspend the minister's refusal.
October 28, 2026 - Alphabet reports $51.4 billion of third-quarter capital spending and free cash flow of minus $9.1 billion.
November 16, 2026 - Residents and Greenpeace file a request to intervene in the court case.
November 25, 2026 - Greenpeace files an emergency request with the minister's office; the office says the 2024 permit remains valid and promises on-site checks.
November 26, 2026 - Inspectors find a near-finished 30,000-square-metre building and verbally order about 300 workers to stop; Google says it is committed to dialogue with the regional government.
November 27, 2026 - Greenpeace issues a press release; regional spokesperson Nicolas Yernaux says a report is going to prosecutors.
January 7, 2027 - Public hearing scheduled at the Conseil d'Etat.

Google faces Finnish order to stop work at 2 data centre sites - Finland's permit agency told a Google subsidiary in October 2026 to suspend land clearing at Muhos and Kajaani.
Local opposition blocked or delayed $156bn of data centre projects in 2025 - Data Center Watch figures and US polling on resistance to new data centres.
How Indianapolis residents beat Google's $1 billion data center proposal - Google pulled a 468-acre rezoning request in September 2025 after a petition campaign.
Alphabet's free cash flow drops to negative $9.1bn despite $26.2bn profit - Third-quarter 2026 capital spending of $51.4 billion pushed Alphabet's free cash flow below zero.
Alphabet advertising revenues climb 14% as Gemini App reaches 750 million users - Fourth-quarter 2025 results and the first 2026 capital spending guidance.
Google cuts operational emissions 2% as AI supply chain emissions rise 25% - Google's 2026 environmental report, including its water replenishment figure.
Amazon is 7x more water-efficient than rivals. Water cost per query: unknown - Amazon's 2025 water figures and what they leave out.
Google breaks ground on its first owned data center in Sweden - An air-cooled design at Horndal, with court permission from 2021.
Google breaks ground on its first Austrian data center, 18 years later - Kronstorf construction began in April 2026 after building-law approval.
Meta data center impacts local water supply in Newton County - A New York Times investigation into one data centre's effect on a Georgia county's water.
Google transfers water storage system to The Dalles, Oregon - Google handed an aquifer storage system and its groundwater rights to the city at no cost in October 2025.

Summary

Who: Google, building through its subsidiary Crystal Computing; the Walloon Region, through delegated official Raphaël Stokis, spokesperson Nicolas Yernaux and minister François Desquesnes; Greenpeace Belgium and local residents, who challenged the project; and Belgium's Conseil d'Etat, which hears Google's appeal.

What: Regional inspectors ordered work stopped on a near-finished 30,000-square-metre data centre building that matched a permit modification the minister had refused, and the region is sending a report alleging illegal construction to prosecutors. The original 2024 permit for three smaller air-cooled buildings remains valid, according to the minister's office.

When: The verbal stop order was given on Thursday, November 26, 2026. The report to prosecutors was announced on November 27, 2026. The court hearing on Google's appeal is set for January 7, 2027.

Where: The Ecopôle business park in Aiseau-Presles, extending into Farciennes and Sambreville, in the province of Hainaut in Wallonia, southern Belgium.

Why: Google's 2025 modification would have merged two planned buildings into one larger data centre cooled with water from the Sambre river. The minister refused it in August 2026 over the facility's water needs during a drought, but construction continued until Greenpeace's emergency request led to the inspection.

you are viewing a single comment's thread
view the rest of the comments
[-] sampleblunderer706@sh.itjust.works 10 points 8 hours ago

It's almost as if these companies repeat offenses when it's profitable to do so

this post was submitted on 28 Nov 2026
112 points (100.0% liked)

Europe

12559 readers
1084 users here now

News and information from Europe 🇪🇺

(Current banner: La Mancha, Spain. Feel free to post submissions for banner images.)

Rules

  1. This is an English-language community. Comments should be in English. Posts can link to non-English news sources when providing a full-text translation in the post description. Automated translations are fine, as long as they don't overly distort the content.
  2. No links to misinformation or commercial advertising. When you post outdated/historic articles, add the year of publication to the post title. Infographics must include a source and a year of creation; if possible, also provide a link to the source.
  3. Be kind to each other, and argue in good faith. Don't post direct insults nor disrespectful and condescending comments. Don't troll nor incite hatred. Don't look for novel argumentation strategies at Wikipedia's List of fallacies.
  4. No bigotry, sexism, racism, antisemitism, islamophobia, dehumanization of minorities, or glorification of National Socialism. We follow German law; don't question the statehood of Israel.
  5. Be the signal, not the noise: Strive to post insightful comments. Add "/s" when you're being sarcastic (and don't use it to break rule no. 3).
  6. If you link to paywalled information, please provide also a link to a freely available archived version. Alternatively, try to find a different source.
  7. Light-hearted content, memes, and posts about your European everyday belong in other communities.
  8. Don't evade bans. If we notice ban evasion, that will result in a permanent ban for all the accounts we can associate with you.
  9. No posts linking to speculative reporting about ongoing events with unclear backgrounds. Please wait at least 12 hours. (E.g., do not post breathless reporting on an ongoing terror attack.)
  10. Always provide context with posts: Don't post uncontextualized images or videos, and don't start discussions without giving some context first.

(This list may get expanded as necessary.)

Posts that link to the following sources will be removed

Unless they're the only sources, please also avoid The Sun, Daily Mail, any "thinktank" type organization, and non-Lemmy social media (incl. Substack). Don't link to Twitter directly, instead use xcancel.com. For Reddit, use old:reddit:com

(Lists may get expanded as necessary.)

Ban lengths, etc.

We will use some leeway to decide whether to remove a comment.

If need be, there are also bans: 3 days for lighter offenses, 7 or 14 days for bigger offenses, and permanent bans for people who don't show any willingness to participate productively. If we think the ban reason is obvious, we may not specifically write to you.

If you want to protest a removal or ban, feel free to write privately to the admin that applied the rule (check modlog first to find who was it.)

founded 2 years ago
MODERATORS